How much capital a BOI project requires depends on the specific activity, rather than a single fixed amount. In practice, four separate requirements need to be considered: the BOI’s minimum investment requirement for the activity, the company’s registered capital, the amount of that capital that must be paid up, and the deadline for paying it up. For the wider requirements beyond capital, see BOI requirements.

Minimum Investment

The BOI's general minimum investment is 1 million baht per project, excluding the cost of land and working capital, unless the specific activity you're applying under sets a different figure. Most promoted activities carry their own conditions on top of this baseline, so 1 million baht is a floor rather than a number you can rely on for every project.

What counts towards it is broadly the fixed investment in the project itself, such as machinery, equipment and buildings. Land and working capital sit outside the calculation.

Check BOI eligible activities for how to find your activity on the list and its specific conditions before relying on a total.

Registered Capital and Paid-Up Capital

Minimum investment isn't the same as registered capital. Minimum investment is what the BOI requires you to commit to the project; registered capital is what your company is registered with at the Department of Business Development, a company law concept rather than a BOI one.

A project's minimum investment can sit well above what an ordinary company would need to register as capital, particularly for activities with a high investment threshold. Your registered capital needs to reflect the BOI requirements.

Paid-up capital is the part of that registered capital actually paid in, rather than pledged, and follows the general rules that apply to any company registration in Thailand. See registered capital in Thailand for how registered and paid-up capital work, and what the DBD currently asks you to show as evidence of it. This page covers what's specific to a BOI project on top of that.

How Capital Needs Differ by Activity

The BOI doesn't set one minimum investment for every project. Some activities carry a much higher threshold than the general 1 million baht floor. Others use a different basis for the calculation entirely rather than a lump investment figure, and a small number of knowledge-based activities carry no minimum investment requirement at all.

Software, digital platform and digital content projects, for example, are assessed on annual spend on salaries for the Thai IT personnel the project employs, rather than a one-off investment amount. Manufacturing and other capital-intensive activities can sit well above the general floor, sometimes by a wide margin, depending on the equipment and scale the activity calls for.

The list itself moves. The BOI refreshed its promotion measures for 2026 to 2027 in January 2026, widening incentives for activities such as advanced manufacturing, EVs and R&D. What applied to an activity last year isn't guaranteed to still apply, so check the current announcement rather than an older summary, including this one.

Investment size affects how your application is handled, separate from the minimum figure itself. Larger projects face a longer review:

Investment size (excluding land and working capital) Typical review time
Up to 200 million baht About 40 working days
200 million to 2,000 million baht About 60 working days
Over 2,000 million baht About 90 working days

Very large projects also typically need a feasibility study and go to the Board itself for review, rather than being cleared at officer level. Confirm current timelines with us, since these shift as caseloads and policy change.

Check your project against the exact activity on the BOI's list before relying on a figure. See BOI eligible activities.

When to Transfer Capital

Capital need not be in place at the point of application. It must be paid up in full before the promotion certificate is issued, since evidence of the transferred funds forms part of the documentation the Board requires in order to issue it.

The sequence following approval is fixed. The promotion is accepted within thirty days of notification, the capital is transferred from overseas within four months of acceptance, and the company is registered within six months where it is not already incorporated. The certificate follows the submission of a complete set of supporting documents, of which proof of the capital transfer is one.

Capital should be brought in after approval rather than before, and as a single transfer for the exact sum required. Funds arriving early, or in several smaller instalments in place of one exact amount, invite enquiry from the Board and delay issue of the certificate.

For the general rules governing registered and paid-up capital, see registered capital in Thailand. The sequence above corresponds to Step 5 of the process set out in apply for BOI promotion.

Planning a BOI project?

We work out the capital your activity needs and when it must be paid, before you apply. See our BOI application service or get in touch for a free consultation.

FAQs

How much does it cost to set up a BOI company in Thailand?

Applying for BOI promotion incurs no government or application fee from the Board of Investment itself. Your primary financial commitment remains your project investment and paid up capital. Ancillary expenses include standard Department of Business Development (DBD) statutory incorporation fees and professional legal or advisory costs. These are based on project scale and complexity.

What is the minimum investment for BOI promotion?

The general minimum is 1 million baht per project, excluding land and working capital, though many activities set a higher or different figure in their own conditions. Check your specific activity before relying on the general number.

Is the minimum investment the same as registered capital?

No. Minimum investment is what the BOI asks you to commit to the project itself. Registered capital is what your company is registered with at the Department of Business Development, a separate, company law concept. The BOI's review centres on the minimum investment, not on registered capital as such. They must reconcile.

How much of a BOI company's registered capital must be paid up, and when?

All of it, before the promotion certificate is issued. Evidence of the transferred funds forms part of the documentation the Board requires in order to issue the certificate. Capital is transferred within four months of accepting the promotion, and should be sent as a single transfer for the exact sum required, since instalments invite enquiry and delay.

Do BOI companies need 2 million baht of registered capital for each work permit?

No, that is the rule for ordinary companies. Since 2025, foreign staff at BOI-promoted companies are assessed against minimum monthly salary thresholds by position instead, from 150,000 baht for executives down to 35,000 baht for some skilled roles, so work permits follow from the BOI approval rather than a fixed capital-per-permit ratio.

Does the capital needed change by BOI activity?

Yes. Some activities sit well above the general 1 million baht floor. Others are assessed on a different basis entirely, such as annual staff salary spend for software and digital projects, and a few carry no minimum investment requirement at all.

Can a BOI company increase its capital later?

Yes. Increasing registered capital works the same way for a BOI company as for any Thai company, through a shareholder resolution and a filing with the Department of Business Development. Tell the BOI too, since your project's capital position is part of what it tracks through ongoing compliance reporting.